铅丝笼组装 |
添加时间:2017/10/19 15:24:08 浏览次数: |
铅丝笼组装:
Wire cage assembly:
(1)石笼单元是成套运至工程现场的。施工人员首先将各片直立,确保各片在准确的位置。
(1) the stone cage unit is transported to the engineering site. The construction staff first erect each piece to ensure that each piece is in the exact position.
(2)绑扎石笼的四个角点,绑扎可以采用绑扎丝或者金属环扣。
(2) binding the four corners of the stone cage, binding can use binding wire or metal ring buckle.
(3)用绑扎丝或者金属环扣将隔片和网身进行连接。
(3) connect the spacer and the net body with binding wire or metal ring buckle. |